Sealed
Clamshell Dredging Method
Clamshell dredging could occur from either a barge within
the river channel or from the top of a levee, depending
on restrictions caused by vegetation on channel banks
or the width of a channel. Barge clamshell dredges are
not self-propelled and would therefore need a small
tugboat to maneuver within the channel. From a barge,
the operation would begin when the bucket assembly,
attached by a long arm (up to 100 feet) is lowered,
in the open position, into the water and allowed to
settle into the channel bottom to collect sediments.
As the dredge operator pulls the bucket up it closes
on the sediment, pulling out up to 5 cubic yards of
water-sediment mix. The dredge operator can then deposit
the water-sediment mix in either a runoff management
basin constructed on the landside of the levee adjacent
to the channel, or onto a barge that would move it to
a runoff management basin in a different location. The
clamshell dredge may also sit atop the levee and scoop
up to 5 cubic yards of water-sediment mix from the channel
bottom, using the same method as from a barge, and deposit
the dredged material into a runoff management basin.
A runoff management basin is typically
rectangular in shape and uses the levee as one of its
walls. The remaining three walls are constructed of
compacted local soil. The three constructed walls would
not exceed 6 feet in height. Runoff management basins
are necessary to contain the 50% moisture sediment-mixture
and prevent drainage into agricultural ditches and channels.
The mixture would reach 25% moisture content in 2 to
6 weeks, depending on the climate and the thickness
of the spread. Once the material loses half of its original
water content, it may be used beneficially for levee
reinforcement or for agricultural soil supplement.
The clamshell dredging method can be
more cost efficient than the hydraulic method, when
sediment spoil areas are immediately adjacent to the
dredged area. However, it can cause greater disruption
to channel vegetation when the bucket scrapes layers
of sediments from the channel bottom. This method would
likely be used in situations where there is limited
space for settling ponds, the likelihood of major disruption
to vegetation and other organisms in the channel bottom
is minimal, the area to be dredged is small, there are
channel islands, or when there are no issues concerning
temporary turbidity and sedimentation in the water.
It is possible, however, to reduce turbidity generated
by this method through the implementation of dredging
practices such as lowering and raising the clamshell
bucket slowly, or using a closed bucket as proposed.
Conveyance
Dredging
In addition to the dredging required to construct the
gates, portions of West Canal, Middle River, and Old
River would be dredged to improve conveyance and the
operation of private agricultural siphons and pumps.
. Approximately 250,000 cubic yards of material would
be dredged and spoiled within the south Delta. Dredging
would be conducted in the center of the channel to avoid
tidal emergent wetlands and riparian habitat. Conveyance
dredging would be conducted using either a sealed clamshell
dredge or hydraulic dredge, as described below. A decision
on which method to use would be made prior to commencing
work, based on access, sediment composition, and potential
impacts on vegetation and other organisms. Conveyance
dredging in Middle River, West Canal, and Old River
to the east of the CVP intake would occur between August
1 and November 30 to minimize effects on delta smelt
and juvenile salmonids.
Hydraulic
Dredging Method
The hydraulic dredging method siphons a water-sediment
mix (four parts water for every one part sediment) from
the bottom of a channel and deposits it into a settling
pond to dry. A dredging barge within the channel lowers
a pipe into the bottom sediment. The pipe siphons the
sediment-water mix into a flexible pipe that may be
inexpensively extended up to 1,000 feet up or down the
channel. This pipe may be weighted down to avoid interfering
with boat navigation adjacent to the project site. The
flexible pipe is attached to a semi-permanent, stationary
pipe that is braced to the waterside of the levee, extends
across the top, and down the landside of the levee into
the primary basin of a settling pond. The flexible pipe
would allow the barge to move relatively far from the
stationary pipe, allowing more dredged area per settling
pond. The stationary pipe would range from 8 to 18 inches
in diameter and would require that gravel be placed
on either side to create a ramp over the pipe for vehicles
and agricultural equipment. The direct deposition of
the material into settling ponds on adjacent lands allows
uninterrupted dredging up to the capacity of the settling
pond. Up to 5,000 cubic yards of material may also be
transported to settling ponds by barges. The settling
ponds would be constructed on the landside of the levee
adjacent to the channels, and would be used for the
decanting process, effectively separating the sediment
from the water and allowing dried material to be put
to beneficial use. The ponds would be constructed of
local compacted soils to avoid toxicity and erosion
of their sides. Settling ponds are typically composed
of three basins: primary, secondary, and return basins.
The primary and secondary basins serve to settle sediments
out of the dredged mix. When water reaches the return
basin, most suspended sediment has settled out of it,
and the water is then pumped back into the channel from
which it was taken. The sediment would take between
24 and 36 days to settle out of the water.
West
Canal
West Canal is a major artery carrying water to the SWP
and CVP. When exports are high and San Joaquin River
flow is low, the velocities in the channel become high
enough to cause scouring and erosion of the channel
bottom. Data collected from a DWR scour monitoring project
at two locations in West Canal indicate erosion of approximately
5 feet of channel bottom within 4 years (reference 1997
to 2001). To reduce these velocities that cause scouring,
West Canal would be enlarged by dredging 3 feet from
the channel bottom between the CCF intake, north to
the point where Victoria Canal meets West Canal. Approximately
40,000 cubic yards of material would be removed. Dredged
spoils would be dried in either settling ponds or runoff
management basins at Widdows Island, depending on the
method used. The hydraulic method would require an area
of approximately 40 acres for spoils ponds, assuming
they can be reused during each dredging phase. No more
than one pond would be necessary to spoil all the dredged
water-sediment mix. The clamshell method would require
no more than 7 acres if runoff management basins were
filled to a depth of 4 feet. Dredging estimates are
based on a dredging efficiency of the 20% solids removal
commonly achieved by hydraulic dredging, and the 50%
solids for clamshell dredging.
Middle River
Middle River would be dredged from the head of Middle
River (at Old River) to approximately 5.3 miles west
to an elevation of –8 msl to accommodate agricultural
siphons and pumps. Dredging would likely be done hydraulically
from a barge. Approximately 200,000 cubic yards of dredged
material would be dredged and spoiled at one or more
drying areas on Union or Roberts Islands, or on Stewarts
Tract. It is estimated that the dredged material would
occupy a total area of up to 165 acres for spoiling
ponds, assuming they can be reused during each dredging
phase. Dredging estimates are based on a dredging efficiency
of the 20% solids removal commonly achieved by hydraulic
dredging.
Old River
There are several agricultural siphons and pumps on
the Old River that provide water for agriculture in
the south Delta. Near the area where Old River, Paradise
Cut, and Tom Paine Slough meet, sedimentation has accumulated
near these siphons and pumps and is affecting the ability
of these siphons and pumps to provide water for agricultural
uses. Dredging in this area would be conducted to improve
siphon and pump operation. The dredging method may be
hydraulic or clamshell dredging by barge, depending
on the areas that are in need of dredging. Approximately
10,000 cubic yards of dredged material would be removed
from the channel and either placed in settling ponds
(hydraulic) or placed in runoff management basins (clamshell)
to dry to an approximate moisture content of 25%. Ponds
and/or basins would be placed on Stewart Tract. It is
estimated that all of the dredged material would occupy
an area of less than 10 acres if done hydraulically
and less than 3 acres if the clamshell method is used.
Hydraulic dredging estimates are based on a dredging
efficiency of the 20% solids removal commonly achieved
by hydraulic dredging, and the 50% solids removed for
clamshell.
Spot Dredging for Agricultural
Diversions in Old River, Middle River, and Victoria,
North, and Grant Line Canals
Dredging in specific areas around siphons in the south
Delta may also be performed as part of the dredging
operation. Siphons that have sediment blockage that
prohibits the effective diversion of water would have
an area up to 100 square feet cleared around them. Siphons
that are –2 msl or shallower would be extended
and dredged around to ensure effective and operable
diversion.
These siphons are located primarily in Old River and
Middle River (outside the areas mentioned above to be
dredged to improve conveyance and remove accumulated
sediment) and in Victoria, North, and Grant Line Canals.
Refer to the Extension of Agricultural Diversions discussion
below for more detail regarding the location of potential
spot dredging. All spot dredging activities would occur
within the channel and would not affect the adjacent
land or levees. A total of up to 44,000 cubic yards
of sediments would be removed from these areas.
Maintenance
Dredging
Maintenance dredging may be necessary to remove collected
sediment in channels as well as near agricultural pumps
and siphons. Depending on the rate of sedimentation,
DWR would perform one round of maintenance dredging
up to 5 years after initial dredging. It is estimated
that up to 25% of the original dredge removal amount
would be necessary for maintenance purposes within this
timeframe. Maintenance dredging and spoiling methods
would be similar to those described above. A formal
dredging plan with additional details on specific maintenance
dredging activities will be developed prior to dredging
activities.
Disposal
of Dredged Materials
Each method of dredging (sealed clamshell and hydraulic)
would effectively dry the material so that it could
be beneficially used in the south Delta. Approximately
5% of all the spoils would be used for levee reinforcement.
The semi-dry material would be placed approximately
1 foot deep on the landside of existing levees. This
would cover any holes or cracks and would therefore
improve the stability of the levee system in the south
Delta. To avoid any impacts on sensitive vegetation
and wildlife, areas of levees with vegetation would
not be reinforced. The other 95% of the material would
be spread over agricultural land at an approximate depth
of 1 foot and could improve the quality of the existing
soil. According to the Section 404 permit issued for
previous dredging in the Grant Line Canal, The results
of the physical measurements, chemical analyses, and
other tests on these sediments indicate that they would
be suitable for most reasonable uses, which may include
levee stabilization, upland, or agricultural applications.
Dredged material would be tested prior to dredging,
during dredging and prior to disposal of the dredge
material for reuse.
|